• No results found

Physical interconnection costs – note for OPTA

N/A
N/A
Protected

Academic year: 2021

Share "Physical interconnection costs – note for OPTA "

Copied!
3
0
0

Bezig met laden.... (Bekijk nu de volledige tekst)

Hele tekst

(1)

14895-372 Final

Physical interconnection costs – note for OPTA

12 September 2011 • 14895-372 Final

1 Introduction

As part of OPTA’s work to close the setting of regulated wholesale interconnection tariffs, OPTA has asked Analysys Mason to update the calculation of physical interconnection costs to ensure that they are presented on a ‘plus BULRAIC’ cost basis.

2 Calculations

OPTA presented the following physical interconnection cost components in 2010.

Figure 1: Interconnection cost components [Source: Final results, 20 April 2010]

In this calculation, preparation, network testing and maintenance charges were composed entirely of an hourly manpower calculation (effort × hourly rate).

The equipment components were calculated from a proportion of annualised costs associated with:

·

purchasing the gateway or port cards

·

installing and commissioning the equipment

·

associated operating expenditures such as maintenance, support, etc.

(2)

Physical interconnection costs – note for OPTA | 2

14895-372 Final

The space component cost, as indicated includes a variety of cost elements. Each of these covers similar annualised cost elements as in the equipment component costs.

The issue of whether the calculated results are ‘plus BULRAIC’ depends essentially on the amount of common costs incorporated in the relevant component cost calculations. Specifically, the main fixed network cost model also contains various annualised asset costs, to which is added a mark-up for common costs (the ‘plus’). The calculated mark-up is for business overheads (approximately 5% equi-proportional mark-up to incremental network costs).

The staff cost associated with the interconnection team (approx. 4 FTE) has been pre-extracted from the business overhead department before the subsequent network cost calculations.

In addition, the fixed model contains network building costs. These building costs are shared out according to the traffic passing through the buildings (which depends on the functional layer of the building). As a result of the existing allocation of building costs, the plus BULRAIC of interconnection traffic minutes already incorporates a share of building space costs.

3 Conclusions

Preparation, network testing and maintenance cost components are based on an hourly manpower charge which is extracted as proportion of business overhead costs. The hourly manpower charge covers the entire per-hour costs of the interconnection team’s work – their direct wages plus a share of all indirect costs (office space, fixtures and fittings, vehicles, support, IT, HR, management, admin, etc.). To add a further buildings or business overhead mark-up to these hourly costs would be double-counting.

As the plus BULRAIC of interconnection traffic minutes already includes a relevant share of building space costs, it is not necessary to add a building space mark-up to the equipment costs contained in the physical interconnection calculation.

However, a 5% business overhead mark-up to interconnection equipment has not been included in the physical interconnection cost calculation. Therefore Equipment and space components of physical interconnection should be increased by 5% to account for the business overheads on technical activities. This would ensure a full coverage of plus BULRAIC costs for these physical interconnection activities.

Updated results (rounded) are shown below.

(3)

Physical interconnection costs – note for OPTA | 3

14895-372 Final

Figure 2: Plus BULRAIC physical interconnection cost components [Source: Analysys Mason]

67 2117

356

Referenties

GERELATEERDE DOCUMENTEN

More related to this research project, building simulation programs do not deal with activities performed by building occupants and with the resulting utilisation of space

The preliminary option space derived from real-life design projects student design project and interviews with practitioners consists of a large number of attributes, four

In the hospital industry the best cost performer has two times less number of workplaces and earns three times more per workplace on IT and has a two times higher IT maturity

The flgures can be completed wlth a text in braille by in· sertlng the drawing sheets (backed by a sheet of braille paper) into a regular braillewriter. For explalning and

Speech technology is used here as general term for electronic speech processing, including automatic speech recognition, speech synthesis and other kinds of

(i) For each vertex of the interconnection architecture, we obtain a behavior relating the variables that ‘live’ on the terminals of the module that is associated with this

We formulate a bound on the performance of these schemes and show that in 99% of upstream DSL channels the linear zero-forcing canceler achieves 97% of the theoretical